The capital of the Xinjiang Uygur Autonomous Region gained its second metro line on November 15, when the northern section of Urumqi Line 2 began carrying passengers between Huashan Street and Nanmen.
The new stretch runs 13.94 kilometers and serves ten stations through the city’s fast-growing northern districts. Its most significant stop may be Urumqi Railway Station, the city’s principal long-distance rail hub. Until now, travelers arriving on intercity trains had to continue their journeys by bus, taxi or car; the opening gives them a direct metro connection for the first time.
Line 1, which opened in 2018, runs between the international airport and Santunbei on the opposite side of the city. It remains the only rail crossing on the network until Line 2 is completed in full. Once the southern section is finished, Line 2 is planned to stretch about 20 kilometers with 16 stations between Yan’an Road and Huashan Street, interchanging with Line 1 in the city center.
Building rapid transit in Urumqi presents unusual challenges. Winter temperatures can drop below minus 20 degrees Celsius, and the city sits farther from an ocean than almost any major city on Earth. Engineers have had to account for deep frost, expansive soils and short construction seasons.
For residents, the line changes daily routines in neighborhoods that were built largely around buses. Commuters from the north now avoid some of the city’s most congested roads, and the route supports a municipal push to concentrate new housing and services around transit stations.
A short airport branch tied to the wider Line 2 project opened in April 2025 as an airport rail link, but Sunday’s opening extends full metro-standard service, with longer trains and regular all-day headways, deep into the northern urban area.
Urumqi is one of several frontier-region cities expanding urban rail as part of a national plan to modernize inland centers. Expansion projects of this kind are typically justified less by immediate profitability than by congestion relief, more balanced land use and better access for workers who do not own cars.
City officials said the remaining southern section will continue construction, with opening dates to be announced after testing. Fares on the new section follow the network’s existing distance-based scale, keeping the metro among the cheapest ways to cross a city that sprawls more than many visitors expect.